Informazioni sul documento
- Università
- Politecnico di Milano
- Corso di laurea
- Aerospace Engineering
- Materia
- Gestione dei Progetti Aerospaziali
- Anno accademico
- 2025-2026
- Classificazione
- Altro materiale
- Formato originale
- Testo
- Testo ricercabile
Materiale universitario di Gestione dei Progetti Aerospaziali per il corso di Aerospace Engineering presso Politecnico di Milano. Il documento tratta: Gestione dei Progetti Aerospaziali Project Work POLITECNICO DI MI LANO De partment o f Man age me nt, Econ omics an d Ind ustrial En gine erin g 2 Group project work – Key dates • Project work launch and presentation April 24th 2026 • Q&A sessions will be organized on May 8th…
Materiale universitario di Gestione dei Progetti Aerospaziali per il corso di Aerospace Engineering presso Politecnico di Milano. Il documento tratta: Gestione dei Progetti Aerospaziali Project Work POLITECNICO DI MI LANO De partment o f Man age me nt, Econ omics an d Ind ustrial En gine erin g 2 Group project work – Key dates • Project work launch and presentation April 24th 2026 • Q&A sessions will be organized on May 8th…
Qualità dell’importazione: il testo è stato estratto direttamente dal documento originale.
Passaggi rappresentativi riconosciuti nelle diverse parti del materiale. Il testo completo resta presente nella pagina per la ricerca, mentre l’anteprima compatta rende più semplice la lettura.
POLITECNICO DI MI LANO De partment o f Man age me nt, Econ omics an d Ind ustrial En gine erin g 2 Group project work – Key dates • Project work launch and presentation April 24th 2026 • Q&A sessions will be organized on May 8th and May 15th to answer questions and doubts on the provided information and tasks (hint: use these moments to work with your group on your project) • Deadline for submission through the WeBeep platform: May 29th 2026 • The evaluation of the project work will be valid till February 2027
6 Assembly sequence STAGE 5 STAGE 4 • 1.3.4.2 AIR VEHICLE SYSTEM • 1.3.4.1 PLANE SOFTWARE STAGE 3 TRANSMISSION • 1.3.6 • 1.3.5 PLANE ENGINE PROPULSION •1.3.3 ELECTRICAL • 1.3.7 AUTOMATIC FLIGHT CONTROL STAGE 2 • 1.3.1.3 TAIL STRUCTURE • 1.3.2.1 FLIGHT CONTROLS • 1.3.2.2 HYDRAULIC STAGE 1 • 1.3.1.1 PLANE CABIN STRUCTURE • 1.3.1.2 FORWARD CABIN STRUCTURE • 1.3.1.4 REAR FUSELAGE
Airplane project description The contract requires the Design, Development and Production of a specific Airplane Variant and the delivery of 4 Test Vehicle (TV) and 5 Pilot Production products (PP). The Project Organization is based on six customer led IPTs: Programme Management (PM) System Engineering (SE) Basic Vehicle Hull Guiding system Missionization Control cabin Supportability Service cabin Test and Evaluation Plans Hydraulic systems Fixed structure Electrical systems Door Power systems Upper panel Basic Structure Rear Assy
Controlling: Airplane project description • The project work refers to the Control Cabin including Design and Development and Manufacturing phases. • The IPT is composed by IPT Leader (BROWN J) and 5 CAMs responsible for specific Control Accounts: • Bianchi R. (Door/Staircase Engineering) • Jack K. (Production Engineering /Production) • Rossi A. (Upper Panel Engineering) • Union J. (Basic Structure/Rear Assy Engineering) • Verdi C. (Fixed Structure Engineering) • The Control Cabin is required during the 1st stage to allow the joint with the Main Cabin Structure. That makes it critical to the beginning of Final Assembly.
Second task: change request A commercial Direct Change is coming from the Customer (attachment 8): it is required that Integrated Project Team evaluates together the impact of this modification both from cost and schedule side on hovercraft production. Moreover, it is required to verify the consistency of the development of the modification with the Final Assembly milestones and to eventually propose a minimum of 2 alternative mitigation solutions. A top level schedule and budget has to be produced showing the development and production of the modified handrail and the expected availability date (Procurement Specification, Supplier Development Phase, Critical Design Review and Production). Prepare a report in the format of a powerpoint presentation The report must provide: - A clear description of the evaluation of the change request - A critical evaluation whether to accept or not the change request and how you would address the impacts of the change request