Full exam for Industrial Technologies in the Management Engineering degree programme at Politecnico di Milano. The document covers: Soluzioni per IT 3 Luglio Tipo esame GRUPPO X Esercizio 1 Solution with 2 shifts M1 M2 M3 M4 M5 Number of machines 1 1 1 2 4 Esercizio 2 Best option M1 M2 M3 M4 M5 Best solution (shift) 2 2 2 3 3 Number of machines 1 1 1 1 3 Costo totale a 2 turni: 3.330.000,00 € Esercizio 3
Full exam for Industrial Technologies in the Management Engineering degree programme at Politecnico di Milano. The document covers: Soluzioni per IT 3 Luglio Tipo esame GRUPPO X Esercizio 1 Solution with 2 shifts M1 M2 M3 M4 M5 Number of machines 1 1 1 2 4 Esercizio 2 Best option M1 M2 M3 M4 M5 Best solution (shift) 2 2 2 3 3 Number of machines 1 1 1 1 3 Costo totale a 2 turni: 3.330.000,00 € Esercizio 3
Import quality: text was extracted directly from the original document.
Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.
Soluzioni per IT 3 Luglio Tipo esame GRUPPO X Esercizio 1 Solution with 2 shifts M1 M2 M3 M4 M5 Number of machines 1 1 1 2 4 Esercizio 2 Best option M1 M2 M3 M4 M5 Best solution (shift) 2 2 2 3 3 Number of machines 1 1 1 1 3 Costo totale a 2 turni: 3.330.000,00 € Esercizio 3 Tabella di inizio Products Machines 1 2 3 4 5 6 1 1 1 1 2 1 1 1 3 1 1 1 4 1 1 1 5 1 1 1 1 1 Tabella finale Products Machines 4 3 1 2 5 6 1 1 1 1 56 2 1 1 1 56 5 1 1 1 1 1 55 3 1 1 1 38 4 1 1 1 7 30 28 24 7 7 5 Configurazione celle Products Machines type 1 cell 4,3,1 1,2,5,3 2 cell 2,5,6 5,3,4 Esercizio 4 Number of machines for the designed cells Cell 1 (1,2,5,3) Solution with 2 shifts M1 M2 M3 M5 Number of machines 1 1 1 1 Cell 2 (5,3,4) solution with 2 shifts M3 M4 M5 Number of machines 1 2 3 Number of operators Cell1: 4 Cell2: 6 Domanda 5 Job shop - 2 shift - total cost in 2 years 3.330.000,00 € Job shop - best solution - total cost in 2 years 2.940.000,00 € Cell - 2 shift - total cost in 2 years 2.685.000,00 € Soluzioni per IT 3 Luglio Tipo esame GRUPPO Y Esercizio 1 Solution with 2 shifts M1 M2 M3 M4 M5 Number of machines 1 1 1 2 4 Esercizio 2 Best option M1 M2 M3 M4 M5 Best solution (shift) 2 2 2 3 2 Number of machines 1 1 1 1 4 Costo totale a 2 turni: 3.120.000,00 Esercizio 3 Tabella di inizio Products Machines 1 2 3 4 5 6 1 1 1 1 2 1 1 1 3 1 1 1 4 1 1 1 5 1 1 1 1 1 Tabella finale Products Machines 4 3 1 2 5 6 1 1 1 1 56 2 1 1 1 56 5 1 1 1 1 1 55 3 1 1 1 38 4 1 1 1 7 30 28 24 7 7 5 Configurazione celle Products Machines type 1 cell 4,3,1 1,2,5,3 2 cell 2,5,6 5,3,4 Esercizio 4 Number of machines for the designed cells Cell 1 (1,2,5,3) Solution with 2 shifts M1 M2 M3 M5 Number of machines 1 1 1 1 Cell 2 (5,3,4) solution with 2 shifts M3 M4 M5 Number of machines 1 2 3 Number of operators Cell1:…
First page of the document.