← Back
ExercisesBy topic

Line balancing Suppl

Study material for Industrial Technologies, shared by the Studwiz community and reviewed by moderators.

Industrial TechnologiesBy topic

Document information

What's included in this study material

Study material for Industrial Technologies, shared by the Studwiz community and reviewed by moderators.

Import quality: text was extracted directly from the original document.

Extracted content from the document

Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.

Page 1

1 ANOTHER CASE Operation Work content [minutes] Direct Follower 1 0.2 2 2 0.4 2 3 0.7 3 4 0.1 1 5 0.3 1 6 0.11 1 7 0.32 1 8 0.6 2 9 0.27 1 10 0.38 1 11 0.5 1 12 0.12 0 Cicle Time (CT)= 1 minute Total Work content = 4 minutes In this case we have another link, between operations 8 and 10 Operation Work content minutes 3 0.7 8 0.6 11 0.5 2 0.4 10 0.38 7 0.32 5 0.3 9 0.27 1 0.2 12 0.12 6 0.11 4 0.1 MAXDUR - TASK ORIENTED PROCEDURE (TOP) 1 2 3 4 5 Available 1;2 1;5 1 3,4 3,4 4,6,7 4,6,7 4,6 4 8 8 9,10 9 9 11 12 Allocated 2 5 1 3 3 7 7 6 4 8 8 10 9 9 11 12 Allocated Time 0.4 0.3 0.2 0.7 0.7 0.32 0.32 0.11 0.1 0.6 0.6 0.38 0.27 0.27 0.5 0.12 Cumulative Allocated Time 0.4 0.7 0.9 1.6 0.7 1.02 0.32 0.43 0.53 1.13 0.6 0.98 1.25 0.27 0.77 0.89 𝐸𝑏 = 4 5 ∗ 𝑚𝑎𝑥(0.9; 0.7; 0.53; 0.98; 0.89) = 4 5 ∗ 0.98 = 81.63% MAXDUR – STATION ORIENTED PROCEDURE (SOP) 1 2 3 Available 1;2 1;5 1 3,4 4 3 6,7,8 6,7 6 7,8 7,10 7 Allocated 2 5 1 3 4 3 8 7 6 8 10 7 Allocated Time 0.4 0.3 0.2 0.7 0.1 0.7 0.6 0.32 0.11 0.6 0.38 0.32 Cumulative Allocated Time 0.4 0.7 0.9 1.6 1 0.7 1.3 1.02 0.81 0.6 0.98 1.3 4 5 Available 7 9 11 11 12 Allocated 7 9 11 11 12 Allocated Time 0.32 0.27 0.5 0.5 0.12 Cumulative Allocated Time 0.32 0.59 1.09 0.5 0.62 𝐸𝑏 = 4 5 ∗ 𝑚𝑎𝑥(1; 0.81; 0.98; 0.59; 0.62) = 4 5 ∗ 1 = 80% MAXNFOL – TOP 1 2 3 Available 1;2 1;5 3;4;5 3;4;5 4;5;6;7 4;5;6;7 4;5;6 4;6 4 8 Allocated 2 1 3 3 7 7 5 6 4 8 Allocated Time 0.40 0.20 0.70 0.70 0.32 0.32 0.30 0.11 0.10 0.60 Cumulative Allocated Time 0.40 0.60 1.30 0.70 1.02 0.32 0.62 0.73 0.83 1.43 4 5 Available 8 9;10 9 9 11 12 Allocated 8 10 9 9 11 12 Allocated Time 0.60 0.38 0.27 0.27 0.50 0.12 Cumulative Allocated Time 0.60 0.98 1.25 0.27 0.77 0.89 𝐸𝑏 = 4 5 ∗ 𝑚𝑎𝑥(0.60; 0.70; 0.83; 0.98; 0.89) = 4 5 ∗ 0.89 = 81.63% MAXNFOL – SOP 1 2 Available 1;2 1;5 3;4;5…