1645014776 EX1 LEAN 2022 01 14

Full exam for Operations Management in the Management Engineering degree programme at Politecnico di Milano. The document covers: Exercise 2 (12 points) The Christmas Everyday Company produces high quality professional skis for winter sport teams. The range of this product family is composed by a combination of 5 different sizes and 12 different surface painting. The customer demand is based on a

Operations ManagementFull exam

Document information

What's included in this study material

Full exam for Operations Management in the Management Engineering degree programme at Politecnico di Milano. The document covers: Exercise 2 (12 points) The Christmas Everyday Company produces high quality professional skis for winter sport teams. The range of this product family is composed by a combination of 5 different sizes and 12 different surface painting. The customer demand is based on a

Import quality: text was extracted directly from the original document.

Extracted content from the document

Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.

Page 1

Exercise 2 (12 points) The Christmas Everyday Company produces high quality professional skis for winter sport teams. The range of this product family is composed by a combination of 5 different sizes and 12 different surface painting. The customer demand is based on a combination of five different sizes and 12 surface paintings leading to 60 variants. The average demand is equal to 400 units per day, the daily demand is not so stable (+/- 25%) and everyday all the variants are requested by the customers, who are not willing to wait for the products. Production process: The production system is composed by the following stages: Machining: this stage is 50% of the time dedicated to this family product. There are two operators that use a manual machine and work in parallel on different pieces. Cutting: there are 2 operators that work in parallel in two different tables. Each operator works with manual tools and he does a ll the activities necessary to cut the item: the cutting process is composed by 6 different serial steps that take more or less the same time. A setup is necessary when product size changes; Finishing: there is one operator that uses a manual machine; a setup is necessary when product size changes; Chemical painter: there is one operator that uses an automatic machine. A setup is necessary when the variant changes. Packaging: there is an operator that uses an automatic machine. A setup is necessary when the variant changes. Each shift lasts 8 hours and there are two 15-minutes breaks per shift. All stages (except of machining stage) are completely dedicated to this product family. Upstream the production system, there is a stock of raw material of 3500 pieces. There is no scrap in any process. Stations Cycle Time (sec.) (single operator) Changeover…