Back
ExamFull examSolution only

1692799624 Exam February 2022 solutions

Full exam for Finance and Management of Infrastructure Investments in the Mobility Engineering degree programme at Politecnico di Milano. The document covers: Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that the critical path(s) is (are) concluded after month 15. Consider the possibility to crash the activities as shown in

Finance and Management of Infrastructure InvestmentsFull exam

Document information

What's included in this study material

Full exam for Finance and Management of Infrastructure Investments in the Mobility Engineering degree programme at Politecnico di Milano. The document covers: Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that the critical path(s) is (are) concluded after month 15. Consider the possibility to crash the activities as shown in

Import quality: text was extracted directly from the original document.

Extracted content from the document

Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.

Page 1

Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that the critical path(s) is (are) concluded after month 15. Consider the possibility to crash the activities as shown in the following table. Identify the optimal solution according to a crashing programme. A penalty of 15 000€ for each month of delay is applied in case the project is not concluded before month 14. At the end of each step of the crashing algorithm write which is the margin gained and the critical path/s. Activity Immediate Predecessor Time Optimistic (months) Average Time (months) Time Pessimistic (months) Std. deviation Duration Reduction (months) Total Crashing Cost (€) A - 3 4 5 1 1 35 000€ B A 3 5 13 5 3 30 000€ C A 1 2 9 4 2 60 000€ D B 6 7 8 2 2 10 000€ E B 4 5 6 1 - - F C 5 9 19 7 5 9 000€ G C 5 5 5 0 3 21 000€ H D,E,F,G 2 3 4 1 - - Solution Activity Immediate Predecessor Time Optimistic (months) Average Time (months) Time Pessimistic (months) Expected Duration Std. deviation Duration Reduction (months) Total Crashing Cost (€) A - 3 4 5 4 1 1 35 000€ B A 3 5 13 6 5 3 39 000€ C A 1 2 9 3 4 2 60 000€ D B 6 7 8 7 2 2 10 000€ E B 4 5 6 5 1 - - F C 5 9 19 10 7 5 9 000€ G C 5 5 5 5 0 3 21 000€ H D,E,F,G 2 3 4 3 1 - - 4 73 C 4 70 4 106 B 4 100 10 177 D 10 170 10 155 E 12 172 7 1710 F 7 170 The critical paths are A-B-D-H and A-C-F-H. The project duration is 20 months. Solution 0 44 A 0 40 7 125 G 12 175 17 203 H 17 200 Solution ➢ Path A-B-D-H: P(Duration > 15 ) = P(z > 15−20 1+25+4+1) = 𝑃 𝑧 ≻ −0.90 = 1 − 𝑃(𝑧 > 0.90) = 1-(1-P(z<0.90)) = P(z<0.90) = 81.59% ➢ Path A-C-F-H: P(Duration > 15 ) = P(z < 15−20 1+16+49+1) = 𝑃 𝑧 > −0.61 = 𝑃(𝑧 < 0.61) = 72.91% Exercise 1 Activity Duration Reduction (months)…

Preview

First page of the document.

First page: 1692799624 Exam February 2022 solutions