Document information
- University
- Politecnico di Milano
- Degree programme
- Mobility Engineering
- Subject
- Finance and Management of Infrastructure Investments
- Classification
- Exam · Full exam
- Content
- Solution only
- Original format
- Text
- Searchable text
Full exam for Finance and Management of Infrastructure Investments in the Mobility Engineering degree programme at Politecnico di Milano. The document covers: Titolo presentazione sottotitolo • Milano, XX mese 20XX Exam July 2022 Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that paths A-C-H and A-E-H are concluded after month
Full exam for Finance and Management of Infrastructure Investments in the Mobility Engineering degree programme at Politecnico di Milano. The document covers: Titolo presentazione sottotitolo • Milano, XX mese 20XX Exam July 2022 Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that paths A-C-H and A-E-H are concluded after month
Import quality: text was extracted directly from the original document.
Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.
Titolo presentazione sottotitolo • Milano, XX mese 20XX Exam July 2022 Exercise 1 The manager of a company is responsible for the following project. Using the PERT algorithm identify the critical path. Compute the probability that paths A-C-H and A-E-H are concluded after month 30. Consider the possibility to crash the activities as shown in the following table. Identify the optimal solution according to a crashing programme. A penalty of 30 000€ for each month of delay is applied in case the project is concluded after month 20 (>20 month) . In addition, a market opportunity equal to 45 000€/month is achieved in case the project is reduced by month 20 to month 18. At the end of each step of the crashing algorithm write which is the margin gained and the critical path/s. Activity Immediate Predecessor Time Optimistic (months) Average Time (months) Time Pessimisti c(months) Std. deviation Duration Reduction (months) Total Crashing Cost (€) A - 6 7 14 4 2 74 000€ B - 2 4 12 3 3 45 000€ C A 5 7 15 7 3 45 000€ D A 3 4 5 1 2 1 000€ E A 9 10 11 1 5 80 000€ F B 5 6 7 1 5 10 000€ G B 5 6 19 6 3 9 000€ H C,D,E,F,G 3 5 19 4 - - Solution Activity Immediate Predecessor Time Optimistic (months) Average Time (months) Time Pessimistic (months) Expected duration (months) Std. deviation Duration Reduction (months) Total Crashing Cost (€) A - 6 7 14 8 4 2 74 000€ B - 2 4 12 5 3 3 45 000€ C A 5 7 15 8 7 3 45 000€ D A 3 4 5 4 1 2 1 000€ E A 9 10 11 10 1 5 80 000€ F B 5 6 7 6 1 5 10 000€ G B 5 6 19 8 6 3 9 000€ H C,D,E,F,G 3 5 19 7 4 - - 8 168 C 10 182 0 55 B 5 105 8 124 D 14 186 8 1810 E 8 180 5 116 F 12 187 The critical path is A-E-H. The project duration is 25 months. Solution 0 88 A 0 80 5 138 G 10 185 18 257 H 18 250 Solution ➢ Path A-C-H: P(Duration > 30 ) = P(z > 30−23 16+49+16) = 𝑃…
First page of the document.