← Back
ExamFull examSolution only

Soluzione esame gennaio 2020

Study material for Finance and Management of Infrastructure Investments, shared by the Studwiz community and reviewed by moderators.

Finance and Management of Infrastructure InvestmentsFull exam

Document information

What's included in this study material

Study material for Finance and Management of Infrastructure Investments, shared by the Studwiz community and reviewed by moderators.

Import quality: text was extracted directly from the original document.

Extracted content from the document

Representative passages recognised in different parts of the material. The full extracted text remains available to search, while this compact preview makes the page easier to read.

Page 1

14/01/2021 CRITICAL PATH: A,D,G,H A penalty of 10 000€ for each week of delay is applied in case the project is not concluded before week 13 Activity Predecessor Duration Dur. reduction Crashing cost Saving Benefit- cost A - 3 2 19,5 20 0,5 B A 4 3 15 30 15 C A 6 2 18 20 2 D A 9 1 7 10 3 E B,C 2 - - - - F E 5 2 6 20 14 G D 5 2 12 20 8 H F,G 1 - - - - CRASHING G! but the gain is only 1 week because the activities E and F has only 1 week of slack time thus the gain is better crash D CRASHING D!! 0 3 3 A 0 0 3 3 4 7 B 6 3 10 9 2 11 E 10 1 12 11 5 16 F 12 1 17 3 6 9 C 4 1 10 17 1 18 H 17 0 18 3 9 12 D 3 0 12 12 5 17 G 12 0 17 CRITICAL PATH: A,D,G,H A,C,E,F,H WE GAINED 1 WEEK Activity Predecessor Duration Dur. reduction Crashing cost Saving Benefit- cost A - 3 2 19,5 20 0,5 B A 4 3 15 30 15 C A 6 2 18 20 2 F E 5 2 6 20 14 G D 5 2 12 20 8 C+G OR F+G COST C+G=30 GAIN C+G=20 COST F+G=18 0 3 3 A 0 0 3 3 4 7 B 5 2 9 9 2 11 E 9 0 11 11 5 16 F 11 0 16 3 6 9 C 3 0 9 16 1 17 H 16 0 17 3 8 11 D 3 0 11 11 5 16 G 11 0 16 GAIN F+G= 20 THUS CRASHING (F+G) CRITICAL PATH: A,D,G,H A,C,E,F,H WE GAINED 2 WEEKS Activity Predecessor Duration Dur. reduction Crashing cost Saving Benefit- cost A - 3 2 19,5 20 0,5 B A 4 3 15 30 15 C A 6 2 18 20 2 THE ONLY POSSIBILITY IS TO CRASH A CRASHING A!! 0 3 3 A 0 0 3 3 4 7 B 5 2 9 9 2 11 E 9 0 11 11 3 14 F 11 0 14 3 6 9 C 3 0 9 14 1 15 H 14 0 15 3 8 11 D 3 0 11 11 3 14 G 11 0 14 CRITICAL PATH: A,D,G,H A,C,E,F,H WE GAINED 2 WEEKS POINT 2 TIME NOW=13 BCWP NOW = BCWS AT TIME 10 → Earned schedule = 10 Activity Expected cost real cost POC% A 18 20 100 B 35 40 100 C 40 30 50 D 35 15 20 E 20 5 20 F 30 - 0 G 20 - 0 H 40 - 0 0 1 1 A 0 0 1 1 4 5 B 3 2 7 7 2 9 E 7 0 9 9 3 12 F 9 0 12 1 6 7 C 1 0 7 12 1 13 H 12 0 13 9 3 12 G 9 0 12 1 8 9 D 1 0 9 TOTAL COST = SUM(…

Preview

First page of the document.

First page: Soluzione esame gennaio 2020